- You already know you can compare earned value measures…to evaluate schedule and cost performance.…An earned value graph makes these comparisons easy.…Even better, it might highlight performance trends.…Earned value numbers in a table have two issues.…First, they're overwhelming.…Your eyes just start to cross.…Second, they show earned value measures…as of the current status date.…It's a snapshot in time.…
A graph of earned value over time is much easier to read.…It can also highlight trends in these measures.…So let's generate an earned value over time report.…To do that in project 2013, you go to the report tab.…Remember, in project 2010, you get to reports…on the "Project" tab.…Here on the "Report" tab, in project 2013,…go to the right end of the ribbon…and click "Visual Reports."…The report that we want is "Earned Value Over Time."…I select that in the list.…
I'm gonna keep the usage data at weeks.…All I have to do is click "View" at the bottom right.…That generates the "Earned Value Over Time Report" in excel.…
Author
Updated
11/5/2015Released
5/14/2015Viewers will then learn how to customize fields and generate cool graphical and visual reports. Finally, the course shows how to share various customizations and configurations as well as best practices for managing multiple projects.
- Recalculating duration, work, and units for assignment changes
- Adding, removing, and replacing resources
- Defining part-time resources
- Setting cost rates
- Accounting for overtime costs
- Working with earned value
- Exchanging data with other programs
- Customizing fields and reports
- Sharing customizations
- Sharing resources and linking tasks between projects
Skill Level Intermediate
Duration
Views
Related Courses
-
Management Tips
with Todd Dewett7h 50m Intermediate -
Deke's Techniques
with Deke McClelland156h 54m Intermediate -
Excel 2013 Essential Training
with Dennis Taylor6h 32m Intermediate
-
Introduction
-
Welcome2m 1s
-
-
1. Options for Opening and Saving Project Files
-
2. Mastering Resource Assignments
-
Keeping task duration fixed3m 26s
-
Maintaining total task work3m 33s
-
3. Managing Project Costs
-
4. Working with Earned Value
-
5. Exchanging Data with Other Programs
-
Hyperlinking in Project6m 3s
-
-
6. Customizing Fields
-
Understanding custom fields3m 32s
-
Naming a custom field2m 35s
-
-
7. Customizing Graphical Reports
-
8. Customizing Visual Reports
-
9. Sharing Customizations
-
10. Working with Multiple Projects
-
Creating a master project4m 32s
-
Conclusion
-
Goodbye1m
-
- Mark as unwatched
- Mark all as unwatched
Are you sure you want to mark all the videos in this course as unwatched?
This will not affect your course history, your reports, or your certificates of completion for this course.
CancelTake notes with your new membership!
Type in the entry box, then click Enter to save your note.
1:30Press on any video thumbnail to jump immediately to the timecode shown.
Notes are saved with you account but can also be exported as plain text, MS Word, PDF, Google Doc, or Evernote.
Share this video
Embed this video
Video: Reviewing earned value with a visual report