- Project automatically calculates…labor and material costs based on the…resource rates you use and the assignments you make.…That's almost always the way to go.…What if Project's calculated costs…don't reflect the real costs?…A little known Project option lets you…manually enter actual costs while work is in progress.…Here we have the Gantt Chart in the top half of the screen,…and in the Details pane, the Task Form.…Because we're looking at cost,…I want to apply the Cost Table to the Task Form.…
I right-click, and choose Cost,…and that displays the Cost Table.…Well let's just start with…the first task in this project,…the "Design interview."…When I click that in the table,…now I can see the assignments in the Task Form.…The Architect is assigned,…and there's a cost of $1,000.…I'm going to change % Complete to 50%.…So, in the Task Form,…in the % Complete field, I type 50, and then click OK.…
When I do that, Project calculates the cost.…The scheduled cost for the task is $1,000 for the architect.…If it's 50% complete, Project says,…
Author
Updated
11/5/2015Released
5/14/2015Viewers will then learn how to customize fields and generate cool graphical and visual reports. Finally, the course shows how to share various customizations and configurations as well as best practices for managing multiple projects.
- Recalculating duration, work, and units for assignment changes
- Adding, removing, and replacing resources
- Defining part-time resources
- Setting cost rates
- Accounting for overtime costs
- Working with earned value
- Exchanging data with other programs
- Customizing fields and reports
- Sharing customizations
- Sharing resources and linking tasks between projects
Skill Level Intermediate
Duration
Views
Related Courses
-
Management Tips
with Todd Dewett7h 50m Intermediate -
Deke's Techniques
with Deke McClelland155h 18m Intermediate -
Excel 2013 Essential Training
with Dennis Taylor6h 32m Intermediate -
Photoshop CC 2015 Essential Training
with Julieanne Kost12h 27m Beginner
-
Introduction
-
Welcome2m 1s
-
-
1. Options for Opening and Saving Project Files
-
2. Mastering Resource Assignments
-
Keeping task duration fixed3m 26s
-
Maintaining total task work3m 33s
-
3. Managing Project Costs
-
4. Working with Earned Value
-
5. Exchanging Data with Other Programs
-
Hyperlinking in Project6m 3s
-
-
6. Customizing Fields
-
Understanding custom fields3m 32s
-
Naming a custom field2m 35s
-
-
7. Customizing Graphical Reports
-
8. Customizing Visual Reports
-
9. Sharing Customizations
-
10. Working with Multiple Projects
-
Creating a master project4m 32s
-
Conclusion
-
Goodbye1m
-
- Mark as unwatched
- Mark all as unwatched
Are you sure you want to mark all the videos in this course as unwatched?
This will not affect your course history, your reports, or your certificates of completion for this course.
CancelTake notes with your new membership!
Type in the entry box, then click Enter to save your note.
1:30Press on any video thumbnail to jump immediately to the timecode shown.
Notes are saved with you account but can also be exported as plain text, MS Word, PDF, Google Doc, or Evernote.
Share this video
Embed this video
Video: Editing resource costs manually