In Microsoft Project, part of the Microsoft Office suite, material resources are physical resources consumed by carrying out a project; think of them like your available inventory for projects. Unlike work resources, material resources are not associated with time, so there are fewer fields to manage. This video explains creating a material resource and how Microsoft Project handles the cost fields associated with material resources.
Material resources represent tangible items consumed by a project, like packing…boxes or cases of cider for the new office open house.…Material resources don't have a time component like work resources so you fill-in a few less fields.…To create a material resource, go to the Resource Sheet.…On the View tab, just click Resource Sheet.…Then go to the first blank Resource Name cell and type-in the name of the resource, in this case Cider.…Then when I click the next cell, the Type cell, Project automatically fills…in Work, but we want a material resource, so click the down arrow and then choose Material.…
You see a few fields go away.…Well, you can still fill-in the Initials field, Project puts in the first letter, but that's not that helpful.…So we'll type-in the full name because Cider is fairly short.…You will notice that Maximum units, Overtime Rate, Base Calendar don't have any…values and that's because the Material Resource doesn't have a time component.…But Project does fill-in the Standard Rate field with 0.…
Author
Released
4/18/2013- Choosing the right Project edition
- Creating and saving projects
- Setting up calendars
- Creating individual and recurring tasks
- Linking and timing tasks
- Assigning tasks to resources
- Viewing your data differently with sorting, grouping, and filtering
- Fine-tuning the project schedule
- Understanding baseline, schedule, and actual values
- Reporting on the project status
- Sharing projects<br><br>
- The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
Skill Level Beginner
Duration
Views
Related Courses
-
Excel 2013 Essential Training
with Dennis Taylor6h 32m Intermediate -
Management Tips
with Todd Dewett7h 50m Intermediate -
Access 2013 Essential Training
with Adam Wilbert5h 4m Beginner -
Advanced Microsoft Project
with Bonnie Biafore5h 18m Intermediate
-
Introduction
-
Welcome57s
-
-
1. Working with Project
-
Using the Ribbon4m 19s
-
Finding commands3m 49s
-
-
2. Setting Up Project Files
-
Setting up calendars2m 45s
-
Setting basic options5m 27s
-
3. Creating Tasks
-
Creating a manual task2m 31s
-
Creating a milestone task1m 25s
-
Creating a recurring task4m 18s
-
Creating a summary task4m 8s
-
Displaying summary tasks2m 30s
-
4. Linking and Timing Tasks
-
Linking tasks5m 51s
-
Adding lag or lead time2m 46s
-
Viewing tasks and task links4m 57s
-
-
5. Creating Resources
-
Understanding resources2m 16s
-
Creating a work resource8m 45s
-
Creating a cost resource3m 21s
-
-
6. Assigning Tasks to Resources
-
Finding overallocations3m 56s
-
7. Working with Views
-
Choosing a view4m 50s
-
Working with a table3m 1s
-
Using the Timeline view5m 17s
-
Sorting tasks and resources4m 27s
-
Grouping tasks and resources4m 45s
-
Modifying task bar layout2m 48s
-
Modifying text formatting2m 52s
-
-
8. Fine-Tuning the Project Schedule
-
Reviewing the critical path3m 53s
-
Splitting a task2m 7s
-
Adjusting a work contour2m 53s
-
Leveling resources4m 54s
-
Inactivating a task2m 41s
-
-
9. Tracking and Managing a Project
-
Adding tasks to a baseline5m 54s
-
Updating the schedule8m 45s
-
Assigning overtime4m 35s
-
Updating costs2m 15s
-
Rescheduling unfinished work3m 45s
-
10. Viewing and Reporting Project Information
-
Using earned value5m 12s
-
Printing views and reports4m 22s
-
11. Sharing Projects
-
Saving to other formats5m 27s
-
Importing and exporting5m 47s
-
-
Conclusion
-
Next steps56s
-
- Mark as unwatched
- Mark all as unwatched
Are you sure you want to mark all the videos in this course as unwatched?
This will not affect your course history, your reports, or your certificates of completion for this course.
CancelTake notes with your new membership!
Type in the entry box, then click Enter to save your note.
1:30Press on any video thumbnail to jump immediately to the timecode shown.
Notes are saved with you account but can also be exported as plain text, MS Word, PDF, Google Doc, or Evernote.
Share this video
Embed this video
Video: Creating a material resource